Construction at Rosewood Residences Hillsboro Beach is progressing at full speed as the project rapidly approaches its structural top-off. The development, which is currently under construction, offers a story of intimate oceanfront living situated uniquely between the Intracoastal Waterway and the Atlantic Ocean.
Progress is split across two parcels: Intracoastal Parcel A: Concrete work on the roof level has commenced, with the top-off anticipated in December 2025. Foundations for private ground-floor lanais are currently underway, and plumbing installation is in progress. Oceanfront Parcel B: The concrete shell is now up to Level 9, with its top-off anticipated shortly after, in January 2026. Glass installation is also advancing, extending to the 4th floor, while interior framing and drywall work are progressing on the 2nd floor.
The two parcels are swiftly transforming into an oasis along Hillsboro Beach. Residences at Rosewood Hillsboro Beach start from $6 million, offering buyers an opportunity to begin their next chapter in this exclusive location